If wind speed exceeds the maximum allowed, what should be done?

Prepare for the Massachusetts 1A Hoisting License Exam. Utilize flashcards and multiple choice questions with explanations. Ensure success on test day!

When wind speed exceeds the maximum allowed, the safest course of action is to suspend hoisting operations until it is deemed safe to resume. This is crucial because high winds can pose a significant risk to the stability and safety of lifted loads, as well as to workers and equipment on site.

Safety protocols and regulations typically outline specific wind speed thresholds beyond which hoisting operations should cease to prevent accidents or equipment failures caused by unstable conditions. Continuing operations in adverse weather can lead to dangerous situations, such as the load swinging uncontrollably or equipment tipping over.

In contrast, increasing the load on the hoisting machine or adjusting machine settings would not address the risk of high winds and could further compromise safety. Continuing operations, even cautiously, does not mitigate the potential dangers that high wind speeds present. Thus, suspending operations until conditions improve is the appropriate response.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy